Réactivité des Gestions de Projets

(kopie 1)

OPTIMAS' project managers work closely with the customers assigned personnel providing a single individual who is responsible for maintaining and reporting the daily status. The project managers are supported by an OPTIMAS' assigned team with the necessary disciplines.

(kopie 2)

 

 

(kopie 3)

Examples of fast-track projects in 2009:

  • 6 simultanious DC-motors, 57 days from date of PO.
  • 3 simultanious Starter motors, 60 days from date of PO.
  • 15 simultanious Worm gears, 60 days from date of PO.
  • 12 simultanious Gear housing assemblies including PPAP, 75 days from date of PO.
  • Complex machined oil field tool, including importation of specialized alloy purchased overseas, PPAP completion and production delivery,  90 days from date of PO